![]() |
|
Road Management & Engineering Journal Copyright © 1999 by TranSafety, Inc. |
|
November, 1999 TranSafety, Inc. (360) 683-6276 Fax: (360) 683-6719 |
One of the most effective ways to reduce the hazards of edge dropoffs to road users
and workers that can occur in construction and maintenance zones is the careful
planning and implementation of a traffic control plan (TCP). The Manual on Uniform
Traffic Control Devices (MUTCD), a national standard, recommends a TCP for
construction projects. The Federal Highway Administration (FHWA) requires that a
formal TCP be included in the plans, specifications, and estimates (PS&E) for each
federal-aid project (Federal-Aid Highway Program Manual 6-4-2-12).
The FHWA Traffic Control Devices Handbook provides examples of elements
and considerations that should be part of the planning and contents of a TCP. If the
TCP is to have the intended safety effect, it must be thorough and complete for the type
of work to be performed. The preferred approach would be to follow the FHWA
requirements and include the TCP in the PS&E. Contractor-requested changes should
be approved, in writing, by the responsible agency engineer.
Many TCPs that I have reviewed provide meager information on coordinating and
controlling both the project work and the traffic that must move through, or be detoured
around, the project. On the other hand, TCPs are often ignored by both contractors
and agency engineers. Either case can be fatal to drivers, pedestrians, and workers.
The TCP must receive serious attention from initial planning to completion of the
project. There will be no significant improvement in work zone safety until agencies
and contractors learn the importance of careful planning and execution. If the other
elements of the contract work, such as pavement design, materials, and installation,
were as poorly planned, designed, and executed as most traffic control activities are
there would be few, if any, bridges safe enough to travel on and roadway pavement
would crumble in a short time.
The TCP can be used to eliminate pavement edge dropoffs or reduce the danger when
the drop-off is present overnight. One state requires in its TCP that the contractor not
leave an edge dropoff exposed between lanes of traffic overnight when all lanes must
be opened to traffic. The state explicitly requires that the contractor pave no greater
length of road than can be completed in a work day. A second state has provisions
that where edge dropoffs of 1 1/4-inches, or greater, occur when the surface of existing
pavement is being removed, and if the lanes are open to traffic, then the 1 1/4-inch
drop must be sloped or traffic control devices (TCD) must be placed along the dropoff
to warn drivers of the hazard.
Some states have provisions in their TCPs for either warning of a two-inch dropoff
between the pavement edge and the shoulder, or correction of the hazard. The
warnings, as a minimum, require either barricades, vertical panels, cones, or barrels.
An appropriate TCP should cover all phases of the project that affect traffic. For each
phase there should be precise written directions and drawings, demonstrating how the
traffic control work and the construction are to be coordinated. One major way to
reduce accidents is to shorten the length of road that is under construction at any given
time. For example, some contractors will pave or repave a lane for the entire length of
the project, leaving a dropoff exposed and without warning. Such a dropoff may be
thus exposed for weeks or months at a time. After paving, contractors will then bring
the shoulders up to the level of the lane pavement surface.
By completing shorter sections of the paving and shoulder grading, as well as installing
the pavement markings by the end of the work day, greater safety will be achieved. If
the shorter sections of road cannot be completed in one day, then other provisions
must be made to reduce the hazard and provide warning.
Edge dropoffs must be recognized for what they are--hidden killers. They are often
difficult for the driver to detect, particularly when the depth is a few inches. In addition,
drivers do not recognize the real hazard that a dropoff of 2, 3 or 4 inches can pose
even if they could determine such depths. The agencies and contractors must treat
any edge dropoff as a potential hazard for motorists and workers, and as a financial
threat to themselves if an injury results.
However, when a difference in the elevation of two surfaces cannot be avoided, then
options should be considered, depending on road configuration and traffic conditions.
A few suggestions:
When work zone traffic control is installed there should be provisions for on-site
monitoring to assure the devices are functioning day and night, seven days a week.
The monitoring should involve the aid of the police and other agency personnel.
Complete records of the management of the TCP should be maintained by both the
contractor and agency personnel. The records should include when specific traffic
control devices (TCD) are placed and removed; when contract work activities were
completed; inspection time, date and findings; any repairs made; and complete
documentation of any accidents occurring in the work zone.

Copyright © 1999 by TranSafety, Inc.